Ramsar Airport Gas Transmission pipeline (30”)

 

Project Specifications:

The Main Client: Ramsar Airport Development Execution Co.

Client: 115 Construction Co. (Inc.)

Type of Contract: PC

Date of Contract: 2012

Project Length: 4 Months

Project Progress: Completed

The total length of pipeline path: 2,200 m

Type of pipes: Steel (30”)

 